Cabinet Approves Revised Cost Estimate of Haryana Orbital Rail Corridor (HORC) Project

 

Chandigarh, March 24 – The Haryana Cabinet, which met under the chairmanship of Chief Minister Sh. Nayab Singh Saini here today, approved the revised cost estimate of the ambitious Haryana Orbital Rail Corridor (HORC) Project, reaffirming the state’s commitment to strengthening regional connectivity and boosting industrial growth.

Haryana to Launch Dedicated Citizen Helpdesk for Revenue Grievances; 48-Hour Resolution

The Cabinet approved a revised project cost of approximately ₹11,709 crore, as against the earlier sanctioned cost of ₹5,618 crore. The revision reflects updated cost assessments based on current market conditions, project scope enhancements, and policy changes. The revised estimate had earlier been approved by the Board of Directors of Haryana Orbital Rail Corporation Limited (HORCL), the Special Purpose Vehicle (SPV) responsible for project implementation.

The project is being executed through a joint venture structure under Haryana Rail Infrastructure Development Corporation (HRIDC), with participation from key stakeholders including government agencies and private partners such as Maruti Suzuki India Limited and Allcargo logistics.

Transfers of Officials and Employees Engaged in Census Put on Hold, No Transfers Till March 31, 2027

The increase in project cost can be primarily attributed to multiple factors, including a sharp rise in land acquisition costs, charge in alignment, new bridges in the NCR region, general cost escalation over time, and an increase in GST rates on works contracts from 12 percent to 18 percent. Additionally, changes in railway policies and the need for upgraded technical specifications have contributed to higher construction costs.

The revised estimate also incorporates additional project components and scope enhancements, including modifications to railway yard infrastructure and connectivity improvements in certain sections, which were not part of the original plan. These additions are aimed at improving operational efficiency and ensuring seamless integration with existing and upcoming rail and freight corridors, including the Dedicated Freight Corridor (DFC).

FCR Dr. Sumita Misra inspects Barwala Grain Market, reviews arrangements

Once completed, the HORC project will provide direct rail connectivity to major industrial and logistics hubs such as Kharkhoda, Manesar, and Sohna, while also supporting the development of new townships in the Haryana NCR region. The corridor is expected to play a critical role in facilitating freight movement, reducing transit time, and promoting industrialization in the state.